Company  News  Process technology  Products  Contact  Distribution  Imprint / /
Unguided  Guided  Dead end drilling

Dead end drilling

By dead end drilling, after reaching the target point and withdrawing the augers the smaller diameter product piping is pushed into the steel casings. Once installed the smaller product pipes are held in position whilst the steel casings are retracted back into the starting shaft where they are removed and stored ready for the next bore.

This process can be either non guided or guided depending on the accuracy required.

When making house connections at main collector sewers, the collector sewer wall is cut with a diamond core drill attachment. The smaller diameter product piping is then pushed through the steel casings, and a watertight connection is established by means of a special sealing unit. To complete the procedure, the steel casings are withdrawn into the launch shaft.

With underground connection

Possible applications:

In all soils up to a max. stone size of 60 mm,
2.36" (single stone)
Up to 25 m, 80 ft, borehole length
Connection to collector from DN 500, 19.69"
and larger

Application limits:

Unstable ground
Obstacles > 60 mm, 2.36"

Machines:

BM 150D and BM 400 (with equipment from BM 150 D)


© 2007-2009 Bohrtec GmbH